Skip to Content.
Sympa Menu

fizinfo - [Fizinfo] BNC szeminárium (EN) - Kocsonya András 2024. május 23. 14:00

fizinfo AT lists.kfki.hu

Subject: ELFT HÍRADÓ

List archive

[Fizinfo] BNC szeminárium (EN) - Kocsonya András 2024. május 23. 14:00


Chronological Thread 
  • From: László Bottyán <bottyan.laszlo AT wigner.hu>
  • To: KFKI Kampusz Intezetei <intezetek AT mail.kfki.hu>, Fizinfo <fizinfo AT lists.kfki.hu>
  • Subject: [Fizinfo] BNC szeminárium (EN) - Kocsonya András 2024. május 23. 14:00
  • Date: Mon, 20 May 2024 20:45:39 +0200 (CEST)
  • Authentication-results: smtp012.wigner.hu (amavisd-new); dkim=pass (1024-bit key) reason="pass (just generated, assumed good)" header.d=wigner.hu

English speakers please scroll down.

Tisztelt Kollégák,

A Budapesti Neutronközpont következő (angol nyelvű) szemináriumára

"Efemeral Nuclear Power Plants (Kérészéletű atomerőművek)" címmel,

2024. május 23-én, csütörtök 14:00 órakor kerül sor a

KFKI kampusz 26. épülete tanácstermében.

Előadó: Kocsonya András (HUN-REN EK, Budapest)

Az előadást on-line formában is közvetíteni fogjuk. Az előadásra, illetve utólag a videofelvételre mutató linkeket az old.bnc.hu/News oldalra kitett hirdetésben közöljük.

Minden személyes és on-line érdeklődőt szeretettel várunk.

Az előadás kivonatát lásd alább.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Dear Colleagues,

The next in-person (EN language) BNC seminar entitled:

"Efemeral Nuclear Power Plants"

will be given by

András Kocsonya (HUN-REN EK, Budapest)

on 23 May, 2024 (Thursday) 2 p.m. (KFKI Campus, Bldg 26)

The seminar is also planned to be streamed. Please find the link to the
MS Teams meetup and later to the recorded video in the old.bnc.hu/News announcement.

All in-person and on-line visitors are welcome.

Best regards,

László Bottyán

----------------------------------------------------------------------------------

ABSTRACT

"Efemeral Nuclear Power Plants"

A nuclear power plant project is successful if the plant is built without any major delay, and then goes into operation, without essential malfunctions, without unplanned operation failures and then
completes its planned lifetime, which is typically several decades. However, this is not the case with many nuclear power plants.

- construction may be halted, even at a significant level of readiness
- although the power plant is completed, it may never get into operation
- the power plant may be shut down after a disproportionately short
operating time

We review and analyze a few of such efemeral power plant projects to find the reasons why the given project could not be successfully completed. Based on the lessons learned, we look for additional, possible risks, which may lead to similar cases in the future, both in the world and in Hungary.

"Kérészéletű atomerőművek"

Egy atomerőmű-projekt akkor sikeres, ha az erőmű jelentősebb csúszás nélkül felépül, működésbe lép, lényeges üzemzavarok és nem tervezett leállások nélkül üzemel, majd kitölti a tervezett üzemidőt, ami
jellemzően több évtized. Számos atomerőműnél ez nem alakul ilyen kedvezően.

- az építés félbemarad, akár jelentős készültségi szinten,
- az erőmű elkészül, de sohasem helyezik üzembe,
- az erőművet aránytalanul rövid működési idő után leállítják

Ilyen kérészéletű atomerőműprojektekből tekintünk át néhányat és elemezzük az okokat, amelyek miatt az adott projekt nem tudott kiteljesedni. A tanulságok alapján további lehetséges kockázatokat keresünk, amelyek hasonló esetekhez vezethetnek a jövőben, a világban és Magyarországon egyaránt.


  • [Fizinfo] BNC szeminárium (EN) - Kocsonya András 2024. május 23. 14:00, László Bottyán, 05/20/2024

Archive powered by MHonArc 2.6.19+.

Top of Page